800V直流供电电源架 / 电源边车 · Power
One dense message. Five is the whole budget per supplier reply, so the questions that decide comparability go first.
电源框高度是几个 OU(ORv3为1OU,不是2U)?装几个模块、每个多少kW?最大输出、N+1 下输出、N+N(双路供电)下输出分别是多少kW?例如 6x3kW=18kW最大 / 15kW N+1 / 9kW N+N,或 6x5.5kW=33kW最大 / 27.5kW 5+1。输入是单whip还是双whip、7针通用输入吗、三相是星形还是三角形、电压范围?
Shelf height in OU (ORv3 is 1OU, not 2U)? How many modules at what kW each? Maximum, N+1 and N+N (dual-feed) output in kW - e.g. 6x3kW = 18 kW max / 15 kW N+1 / 9 kW N+N, or 6x5.5kW = 33 kW max / 27.5 kW at 5+1. Single-whip or dual-whip input, 7-pin universal inlet, three-phase wye or delta, and voltage range?
N+N halves usable power. A shelf quoted at its headline kW is quoted at zero redundancy.
母线额定是48V还是51V?在市电中断时电源保持能量耗尽后输出下降多少伏(参考设计为下降3V)触发BBU接管?母线电压高于44V持续0.1秒时是否判定为BBU放电中并进入0-5.5秒随机上电延时(无BBU时为0-2秒)?多台模块是否通过 SYNC_START / Do_SyncReady_L / DI_Sync_H 同步上电?从48V模式切回51V需要多久?
Is the bus nominally 48 V or 51 V? On mains loss, by how many volts does the output fall after hold-up energy is spent, to hand over to the BBU (reference design drops 3 V)? Does bus voltage above 44 V for 0.1 s flag 'BBU discharging' and trigger the 0-5.5 s randomised turn-on window (0-2 s without BBU)? Do modules synchronise turn-on via SYNC_START / Do_SyncReady_L / DI_Sync_H? How long to move from 48 V mode back to 51 V?
Get this wrong and the shelf and the BBU fight each other on restoration; it is the least documented, most failure-prone interface in ORv3.
报价是否包含 PMC(电源框管理控制器,含前面板以太网口和串口调试)和 PMI(Modbus 引出扩展模块)?上游通信协议是 Modbus 还是 PMBus,是否支持 Redfish?通信线束的针位定义(GND、PLS 电源/备电掉电信号、BKP、RS485 A/B)请一并提供。
Does the quote include the PMC (Power Management Controller, front Ethernet plus serial console) and the PMI (Modbus bring-out extension module)? Is upstream comms Modbus or PMBus, and is Redfish supported? Send the comms cable pinout (GND, PLS power-loss signal, BKP, RS485 A/B).
These are separate SKUs in the reference ORv3 system. Buyers discover this after the shelf lands.
该电源在满载时的掉电保持时间(hold-up time)是多少毫秒?在10%/20%/50%/100%负载下的实测效率分别是多少?请提供第三方测试报告或80 PLUS证书查询链接。
What is the hold-up time in milliseconds at full load? Give measured efficiency at 10%, 20%, 50% and 100% load. Provide a third-party test report or the 80 PLUS certificate lookup link.
Hold-up time decides whether a UPS transfer or a brief sag takes the server down. It is never volunteered, and cheap CRPS units cut it first. Efficiency must be quoted at 10/20/50/100% load, not as an 80 PLUS badge.
这批货是全新原封、官翻、拆机件还是工程样片(ES/QS)?请在形式发票上写明状态。如果是拆机件,来源和使用时长是多少?
报价是EXW、FOB还是CIF?指定口岸是哪里?报价里不含哪些费用(出口报关、内陆运输、保险、目的港费用)?
外箱尺寸多少?每箱装几台、毛重多少公斤?每托盘几箱?整单总体积多少立方米?是木托还是纸托、是否需要熏蒸证明?
请给出阶梯报价:1台、10台、50台、100台各是什么价格?每个型号的起订量是多少?价格有效期多久?
出口报关准备用哪个HS编码?报价是含税价还是不含税价?该编码的出口退税率是多少、退税是否已经体现在报价里?
整机原产地写哪里?能否出具原产地证(一般CO还是Form E/RCEP优惠证)?货物是从中国直接出口,还是经香港、新加坡或越南转运?
质保多少个月?DOA(到货即损)申报期限是几天?返修是寄回中国还是有海外备件?是否提供先行换货?返修运费谁承担?
这个托架/导轨/面板是原厂件还是兼容件?上面有没有原厂LOGO或型号标识?能否书面保证不侵犯第三方商标和专利,并承担相关责任?
整机和关键部件(CPU、加速卡、网卡)的原产地分别是哪里?产品里有没有使用美国原产的芯片、软件或技术?大概占多少比例?能不能配合签署最终用户和最终用途声明、承诺不转运?这个型号以前出口过哪些国家?
合同和发票的签约主体全称是什么?统一社会信用代码是多少?工厂是自有还是代工?母公司或控股股东是谁、持股比例多少?有没有国资或上市公司背景?
请提供公司全称、统一社会信用代码和营业执照复印件。贵司是生产工厂、原厂授权代理还是贸易商?如为工厂,工厂地址在哪里、可否安排验厂或视频验厂?开票主体与收款主体是否为同一家公司?
最小起订量是多少?请给出阶梯报价(如100/500/1000/5000片)。报价有效期多少天?NAND和HDD价格波动时如何调价?是否接受锁价?
+ 37 more universal terms